Improving navigation conditions on the Danube between Calarasi and Braila (rkm 375–175)

Year
2017
Abstract
Project fiche covering need (2.5 m depth; 150–180 m width), 11 bottlenecks, status/timeline (suspension 2010; restarts 2011; works finished 2014–2016 at CP10, CP02, CP01), adaptive monitoring, and financing (total €47.84 M; EU €38.26 M; national €9.58 M). Notes reduced crest of the Bala sill (–50%) after 3D modelling and further alternatives study from 2015.
Authors
Cătălina Dumbravă
Publisher
EU Strategy for the Danube Region – Priority Area 1A (Navigation)
Source type
Project Report